A Hybrid Decision-Making Framework to Manage Human Assets in Project Teams Considering Competency Criteria Based on Industry 4.0 and Post-COVID-19 Era | ||
Advances in Industrial Engineering | ||
دوره 58، شماره 2، اسفند 2024، صفحه 391-412 اصل مقاله (857.42 K) | ||
نوع مقاله: Research Paper | ||
شناسه دیجیتال (DOI): 10.22059/aie.2024.372670.1890 | ||
نویسندگان | ||
Saman Abdeiman1؛ Zeinab Sazvar* 2؛ Alireza Mohebi1 | ||
1M.Sc., School of Industrial Engineering, College of Engineering, University of Tehran, Tehran, Iran. | ||
2Associate Professor, School of Industrial Engineering, College of Engineering, University of Tehran, Tehran, Iran. | ||
چکیده | ||
The selection of human assets for teams significantly impacts the success and profitability of projects. Industrial Revolution 4.0 (4IR) and the post-COVID-19 conditions impose requirements on virtual collaboration, bots-human collaboration, and teleworking projects. The matrix-structured organization faces challenges in this process because it requires weighing various criteria from distinct perspectives. Accordingly, an inappropriate team selection process can result in high costs or failure. Team member competency criteria are identified based on 4IR, in this study. The study also evaluates the theory of generations based on the fact that project teams consist of members from different generations, each with unique characteristics. To this end, a multi-objective allocation model is presented that maximizes competency level while minimizing costs, considering the organizational structure, the 4IR, the post-COVID-19 era condition, and the generation theory. The study attempts to provide decision-makers in multiple-project organizations with a realistic picture to make a trade-off between the cost and competency level of teams. The linear best-worst method (BWM) is used to weigh the competency criteria. Regarding the developed bi-objective model, the Augmented ε- Constraint (AUGMECON) method is utilized to solve the problem. The model is also validated using the Iran Mall project. The findings indicate that younger generations have almost 1.3 more competence scores in virtual communication than older generations. Also, the organization should increase expenditures by 7.1% to reach the highest level of competency. | ||
کلیدواژهها | ||
Project Management؛ Theory of Generations؛ Best-Worst Method؛ The Covid-19؛ Virtual Collaboration؛ Multi-Objective Programming؛ Human Resource Management | ||
مراجع | ||
[1] F. Rahmanniyay, A. J. Yu, and J. Seif, “A multi-objective multi-stage stochastic model for project team formation under uncertainty in time requirements,” Comput Ind Eng, vol. 132, pp. 153–165, 2019, doi: 10.1016/j.cie.2019.04.015.
[2] C. Marnewick and A. L. Marnewick, “The Demands of Industry 4.0 on Project Teams,” IEEE Trans Eng Manag, vol. 67, no. 3, pp. 941–949, 2020, doi: 10.1109/TEM.2019.2899350.
[3] A. Pitchai, A. V. Reddy, and N. Savarimuthu, “Fuzzy based quantum genetic algorithm for project team formation,” International Journal of Intelligent Information Technologies, vol. 12, no. 1, pp. 31–46, 2016, doi: 10.4018/IJIIT.2016010102.
[4] A. Richert, M. Shehadeh, L. Plumanns, K. Gros, K. Schuster, and S. Jeschke, “Educating engineers for industry 4.0: Virtual worlds and human-robot-teams: Empirical studies towards a new educational age,” in IEEE Global Engineering Education Conference, EDUCON, Ieee, 2016, pp. 142–149. doi: 10.1109/EDUCON.2016.7474545.
[5] A. J. McNamara and S. M. E. Sepasgozar, “Intelligent contract adoption in the construction industry: Concept development,” Autom Constr, vol. 122, p. 103452, 2021, doi: 10.1016/j.autcon.2020.103452.
[6] J. Jouzdani, “Fight against COVID-19: A global outbreak response management performance view,” Journal of Project Management, vol. 5, pp. 151–156, 2020, doi: 10.5267/j.jpm.2020.3.001.
[7] Y. Hidayat, D. S. Pangestu, Subiyanto, T. Purwandari, Sukono, and J. Saputra, “Predicting the weekly COVID-19 new cases using multilayer perceptron: An evidence from west Java, Indonesia,” Decision Science Letters, vol. 11, no. 3, pp. 247–262, 2022, doi: 10.5267/j.dsl.2022.3.002.
[8] M. A. Brown Sr, M. A. Brown Sr, and D. Miller, “Examining the Influence of COVID-19 on Telework, Trustworthiness, and Performance,” International Journal of Project Management and Productivity Assessment (IJPMPA), vol. 10, no. 1, pp. 1–20, 2022.
[9] O. Elrefaey, S. Ahmed, I. Ahmad, and S. El‐sayegh, “Impacts of COVID‐19 on the Use of Digital Technology in Construction Projects in the UAE,” Buildings, vol. 12, no. 4, p. 489, 2022, doi: 10.3390/buildings12040489.
[10] B. Amade, “Exploring the influence of information and communication technology (ICT) on construction supply chain management: Empirical evidence from a construction project’ s perspective,” vol. 8, pp. 1–14, 2023, doi: 10.5267/j.jpm.2022.7.001.
[11] European Union, “Telework in the EU before and after the COVID-19: where we were, where we head to,” Science for Policy Briefs, vol. 2009, pp. 1–8, 2020.
[12] Y. M. Omar, M. Minoufekr, and P. Plapper, “Business analytics in manufacturing: Current trends, challenges and pathway to market leadership,” Operations Research Perspectives, vol. 6, p. 100127, 2019, doi: 10.1016/j.orp.2019.100127.
[13] V. S. Anantatmula and B. Shrivastav, “Evolution of project teams for Generation Y workforce,” International Journal of Managing Projects in Business, vol. 5, no. 1, pp. 9–26, 2012, doi: 10.1108/17538371211192874.
[14] J. Magano, C. Silva, C. Figueiredo, A. Vitória, T. Nogueira, and M. A. P. Dinis, “Generation Z: Fitting project management soft skills competencies—A mixed-method approach,” Educ Sci (Basel), vol. 10, no. 7, pp. 1–24, 2020, doi: 10.3390/educsci10070187.
[15] A. Potter, H. Al-Kaabi, and M. Naim, “Aircraft maintenance, repair and overhaul,” in The Global Commercial Aviation Industry, 2015, pp. 170–189.
[16] A. Farasat and A. G. Nikolaev, “Social structure optimization in team formation,” Comput Oper Res, vol. 74, pp. 127–142, 2016, doi: 10.1016/j.cor.2016.04.028.
[17] M. Imran, M. Khaliq, A. K. Mahbubul Hye, and K. Ekareesakul, “Influence of risk factors on construction firm project success in pakistan,” Decision Science Letters, vol. 8, no. 3, pp. 285–294, 2019, doi: 10.5267/j.dsl.2018.12.002.
[18] S. Safarzadegan Gilan, M. H. Sebt, and V. Shahhosseini, “Computing with words for hierarchical competency based selection of personnel in construction companies,” Applied Soft Computing Journal, vol. 12, no. 2, pp. 860–871, 2012, doi: 10.1016/j.asoc.2011.10.004.
[19] L. E. Agustin-Blas, S. Salcedo-Sanz, E. G. Ortiz-Garcia, A. Portilla-Figueras, A. M. Perez-Bellido, and S. Jimenez-Fernandez, “Team formation based on group technology: A hybrid grouping genetic algorithm approach,” IEEE Engineering Management Review, vol. 40, no. 1, pp. 30–43, 2012, doi: 10.1109/EMR.2012.6172768.
[20] P. W. G. Morris and J. K. Pinto, The Wiley Guide to Project Organization and Project Management Competencies, vol. 8. John Wiley & Sons, 2010.
[21] A. Baykasoglu, T. Dereli, and S. Das, “Project team selection using fuzzy optimization approach,” Cybern Syst, vol. 38, no. 2, pp. 155–185, 2007, doi: 10.1080/01969720601139041.
[22] G. Blak Bernat, E. L. Qualharini, M. S. Castro, A. B. Barcaui, and R. R. Soares, “Sustainability in Project Management and Project Success with Virtual Teams: A Quantitative Analysis Considering Stakeholder Engagement and Knowledge Management,” Sustainability, vol. 15, no. 12, p. 9834, Jun. 2023, doi: 10.3390/su15129834.
[23] C. Mayer, T. Sivatheerthan, S. Mütze-Niewöhner, and V. Nitsch, “Sharing leadership behaviors in virtual teams: effects of shared leadership behaviors on team member satisfaction and productivity,” Team Performance Management: An International Journal, vol. 29, no. 1/2, pp. 90–112, Feb. 2023, doi: 10.1108/TPM-07-2022-0054.
[24] N. Yavuz Aksakal and E. Ulucan, “Revealing the Leadership Characteristics of the Modern Age: Generation-Z Perspective,” International Journal of Organizational Leadership, vol. 13, no. 1, pp. 22–38, Mar. 2024, doi: 10.33844/ijol.2024.60397.
[25] A. Juras, “Competency Profile of Project Team Members – Interplay with Team Dynamics and Project Success,” in 7th International OFEL Conference on Governance, Management and Entrepreneurship: Embracing Diversity in Organisations (Dubrovnik, 2019), Zagreb: Governance Research and Development Centre (CIRU), 2019, p. 272.
[26] B. Weber, J. Butschan, and S. Heidenreich, “Tackling hurdles to digital transformation -The role of competencies for successful IIoT implementation,” in 2017 IEEE Technology and Engineering Management Society Conference, TEMSCON 2017, IEEE, 2017, pp. 312–317. doi: 10.1109/TEMSCON.2017.7998395.
[27] J. E. Mathieu, J. R. Hollenbeck, D. Van Knippenberg, and D. R. Ilgen, “A century of work teams in the journal of applied psychology,” Journal of Applied Psychology, vol. 102, no. 3, pp. 452–467, 2017, doi: 10.1037/apl0000128.
[28] J. Bajer, “Digital transformation needs the human touch,” Strategic HR Review, vol. 16, no. 2, pp. 91–92, 2017, doi: 10.1108/shr-02-2017-0011.
[29] L. Waizenegger, B. McKenna, W. Cai, and T. Bendz, An affordance perspective of team collaboration and enforced working from home during COVID-19, vol. 29, no. 4. Taylor & Francis, 2020, pp. 429–442. doi: 10.1080/0960085X.2020.1800417.
[30] T. Zuofa and E. G. Ochieng, “Investigating barriers to project delivery using virtual teams,” Procedia Comput Sci, vol. 181, pp. 1083–1088, 2021, doi: 10.1016/j.procs.2021.01.304.
[31] A. Baykasoglu, T. Dereli, and S. Das, “Project team selection using fuzzy optimization approach,” Cybern Syst, vol. 38, no. 2, pp. 155–185, 2007, doi: 10.1080/01969720601139041.
[32] H. Wi, S. Oh, J. Mun, and M. Jung, “A team formation model based on knowledge and collaboration,” IEEE Engineering Management Review, vol. 40, no. 1, pp. 44–57, 2012, doi: 10.1109/EMR.2012.6172769.
[33] B. Feng, Z. Z. Jiang, Z. P. Fan, and N. Fu, “A method for member selection of cross-functional teams using the individual and collaborative performances,” Eur J Oper Res, vol. 203, no. 3, pp. 652–661, 2010, doi: 10.1016/j.ejor.2009.08.017.
[34] L. Zhang and X. Zhang, “Multi-objective team formation optimization for new product development,” Comput Ind Eng, vol. 64, no. 3, pp. 804–811, 2013, doi: 10.1016/j.cie.2012.12.015.
[35] F. Cavdur, A. Sebatli, M. Kose-Kucuk, and C. Rodoplu, “A two-phase binary-goal programming-based approach for optimal project-team formation,” Journal of the Operational Research Society, vol. 70, no. 4, pp. 689–706, 2019.
[36] E. E. Karsak, “Fuzzy multiple objective programming approach for personnel selection,” in Proceedings of the IEEE International Conference on Systems, Man and Cybernetics, IEEE, 2000, pp. 2007–2012. doi: 10.1109/icsmc.2000.886409.
[37] T. L. B. Tseng, C. C. Huang, H. W. Chu, and R. R. Gung, “Novel approach to multi-functional project team formation,” International Journal of Project Management, vol. 22, no. 2, pp. 147–159, 2004, doi: 10.1016/S0263-7863(03)00058-9.
[38] S. J. G. Chen and L. Lin, “Modeling team member characteristics for the formation of a multifunctional team in concurrent engineering,” IEEE Trans Eng Manag, vol. 51, no. 2, pp. 111–124, 2004, doi: 10.1109/TEM.2004.826011.
[39] D. Strnad and N. Guid, “A fuzzy-genetic decision support system for project team formation,” Applied Soft Computing Journal, vol. 10, no. 4, pp. 1178–1187, 2010, doi: 10.1016/j.asoc.2009.08.032.
[40] M. Tavana, F. Azizi, F. Azizi, and M. Behzadian, “A fuzzy inference system with application to player selection and team formation in multi-player sports,” Sport Management Review, vol. 16, no. 1, pp. 97–110, 2013, doi: 10.1016/j.smr.2012.06.002.
[41] F. Cavdur, A. Sebatli, M. Kose-Kucuk, and C. Rodoplu, “A two-phase binary-goal programming-based approach for optimal project-team formation,” Journal of the Operational Research Society, vol. 70, no. 4, pp. 689–706, 2019.
[42] A. Farasat and A. G. Nikolaev, “Social structure optimization in team formation,” Comput Oper Res, vol. 74, pp. 127–142, 2016, doi: 10.1016/j.cor.2016.04.028.
[43] L. Zhang and X. Zhang, “Multi-objective team formation optimization for new product development,” Comput Ind Eng, vol. 64, no. 3, pp. 804–811, 2013, doi: 10.1016/j.cie.2012.12.015.
[44] D. Strnad and N. Guid, “A fuzzy-genetic decision support system for project team formation,” Applied Soft Computing Journal, vol. 10, no. 4, pp. 1178–1187, 2010, doi: 10.1016/j.asoc.2009.08.032.
[45] J. H. Gutiérrez, C. A. Astudillo, P. Ballesteros-Pérez, D. Mora-Melià, and A. Candia-Véjar, “The multiple team formation problem using sociometry,” Comput Oper Res, vol. 75, pp. 150–162, 2016, doi: 10.1016/j.cor.2016.05.012.
[46] E. E. Karsak, “Fuzzy multiple objective programming approach for personnel selection,” in Proceedings of the IEEE International Conference on Systems, Man and Cybernetics, IEEE, 2000, pp. 2007–2012. doi: 10.1109/icsmc.2000.886409.
[47] J. Rezaei, “Best-worst multi-criteria decision-making method,” Omega (Westport), vol. 53, pp. 49–57, 2015.
[48] J. Rezaei, “Best-worst multi-criteria decision-making method: Some properties and a linear model,” Omega (United Kingdom), vol. 64, pp. 126–130, 2016, doi: 10.1016/j.omega.2015.12.001.
[49] P. Bhandari and K. Nikolopoulou, “What Is a Likert Scale? | Guide & Examples,” Scribbr, 2020, [Online]. Available: https://www.scribbr.com/methodology/likert-scale/
[50] G. Mavrotas, “Effective implementation of the ε-constraint method in Multi-Objective Mathematical Programming problems,” Appl Math Comput, vol. 213, no. 2, pp. 455–465, 2009, doi: 10.1016/j.amc.2009.03.037.
[51] P. Pudasaini, “Integrated planning of downstream petroleum supply chain: a multi-objective stochastic approach,” Operations Research Perspectives, vol. 8, p. 100189, 2021, doi: 10.1016/j.orp.2021.100189.
[52] Project Management Institute, “Project Manager Competency Development Framework,” in Project Management Institute, Project Management Institute, 2017, p. 190.
[53] World Economic Forum, “The Future of Jobs Employment, Skills and Workforce Strategy for the Fourth Industrial Revolution,” Growth Strategies, no. january, pp. 2–3, 2016.
[54] A. Davies, D. Fidler, and M. Gorbis, “Future work skills 2020,” University of Phoenix Research Institute, vol. 540, p. 19, 2011.
[55] B. David, “Computer technology and probable job destructions in Japan: An evaluation,” J Jpn Int Econ, vol. 43, pp. 77–87, 2017, doi: 10.1016/j.jjie.2017.01.001.
[56] C. B. Frey and M. A. Osborne, “The future of employment: How susceptible are jobs to computerisation?,” Technol Forecast Soc Change, vol. 114, pp. 254–280, 2017, doi: 10.1016/j.techfore.2016.08.019.
[57] Z. Mohammadi, F. Barzinpour, and E. Teimoury, “Designing sustainable supply chain network by considering direct and indirect shipment: Evidence from food industry,” Decision Science Letters, vol. 9, no. 3, pp. 323–336, 2020, doi: 10.5267/j.dsl.2020.5.003.
[58] M. M. Billal and M. M. Hossain, “Multi-objective optimization for multi-product multi-period four echelon supply chain problems under uncertainty,” Journal of Optimization in Industrial Engineering, vol. 13, no. 1, pp. 1–17, Mar. 2020, doi: 10.22094/JOIE.2018.555578.1529.
[59] Z. Sazvar, M. Rahmani, and K. Govindan, “A sustainable supply chain for organic, conventional agro-food products: The role of demand substitution, climate change and public health,” J Clean Prod, vol. 194, pp. 564–583, 2018.
[60] F. Rahmanniyay, A. J. Yu, and J. Seif, “A multi-objective multi-stage stochastic model for project team formation under uncertainty in time requirements,” Comput Ind Eng, vol. 132, pp. 153–165, 2019, doi: 10.1016/j.cie.2019.04.015.
[61] “Largest shopping centers worldwide as of 2020, by GLA As of 2020, Iran Mall, located in Teheran, was the largest shopping center in the world with 21 million square feet of Gross Leasable Area. This represents approximately 1 . 95 million square mete,” no. October 2020, 2021.
[62] “• Largest malls worldwide, by GLA 2020 _ Statista.”
[63] C. Marnewick and A. L. Marnewick, “The Demands of Industry 4.0 on Project Teams,” IEEE Trans Eng Manag, vol. 67, no. 3, pp. 941–949, 2020, doi: 10.1109/TEM.2019.2899350.
[64] V. S. Anantatmula and B. Shrivastav, “Evolution of project teams for Generation Y workforce,” International Journal of Managing Projects in Business, vol. 5, no. 1, pp. 9–26, 2012, doi: 10.1108/17538371211192874.
[65] B. Weber, J. Butschan, and S. Heidenreich, “Tackling hurdles to digital transformation -The role of competencies for successful IIoT implementation,” in 2017 IEEE Technology and Engineering Management Society Conference, TEMSCON 2017, IEEE, 2017, pp. 312–317. doi: 10.1109/TEMSCON.2017.7998395.
[66] N. A. S. Insights, “Generation Y: the millennials,” Accessed on, vol. 16, p. 2019, 2006. | ||
آمار تعداد مشاهده مقاله: 462 تعداد دریافت فایل اصل مقاله: 30 |